4: Project Timeline: 2003/04

Time Coordination/
Technical team
Provincial Advisory Group (PAG) Demonstration Site Agents (DSAs) and Local Working Groups (LWGs) Deliverables
March, 2003 HC/Laidlaw proposals
Coordinator hired
    Proposals accepted/funded
April PAG Selection
Prepare Working Budget/adjust to OPC format
Project Timeline developed
PAG Briefing Notes developed
Technical team selection (Admin, Research, Commun., Indicators)
Evaluator selection process begins
Develop PAG Meeting Agenda
    PAG confirmed
Working Budget adjusted to OPC format
Project Timeline finalized
PAG Briefing Notes finalized
Technical team contracted
PAG Briefing Notes/Meeting Agenda distributed
May Technical team briefings to prep PAG meeting
PAG minutes prepared
1st PAG Meeting:
Defining Inclusion and Criteria for Indicators Discussion
DSAs selection process. Preliminary Indicators finalized
PAG minutes delivered
June Technical team:
1st Working
DraftIndicators preparation
Draft Engagement Strategies developed
Evaluation tools and methods developed
2nd PAG Meeting:
Defining Inclusion and Criteria for Indicators
Discussion, contd.
DSA selection finalized
LWGs organized.
DSAs contracted
Engagement Strategies finalized
1st Working
Draft Indicators finalized
July Coordinator/Evaluator Site Visits   1st LWG Meetings:
Finalize Engagement Strategies Demonstration with 1st Working Draft Indicators in four sites
Demonstrations begin with Evaluation tools and methods in place
LWG minutes delivered.1st Quarter Report
August Coordinator/Evaluator Site Visits   Demonstration with 1st Working Draft Indicators in four sites, contd. Demonstrations, contd..
September Technical team:
2nd Working
Draft Indicators
  2nd LWG Meetings:
Demonstration
Review: 1st
LWG minutes delivered
2nd Working Draft Indicators finalized
October Technical Team:
Final
Draft Indicators
3rd PAG Meeting:
2nd Working
Draft Indicators Review
  PAG minutes delivered.
2nd Quarter Report Final Draft Indicators finalized
November Coordinator/Evaluator site visits   Demonstration with Final Draft Indicators  
DecemberDec., contd. Coordinator/Evaluator site visits   Demonstration, contd.3rd LWG Meetings:
2nd Demonstration Review
LWG minutes delivered.
January, 2004 Technical Team: Approved Indicators 4th PAG Meeting:Final Draft Indicator Review   3rd Quarter Report
Report to Laidlaw Foundation.
PAG minutes delivered.
February, 2004   5th PAG Meeting:
Approved Indicators Approval
  Approved Indicators finalizedPAG minutes delivered.
March, 2004 Coordinator, Technical Team, Local Agents confer
Evaluator prepares report
Coordinator/Writing & Plain Language Consultants
    Evaluation finalized
Final Report finalized
Final Report to Health Canada.

The opinions expressed in this project do not necessarily reflect the official views of Health Canada, Population Public Health Branch, now the Public Health Agency of Canada, or the Laidlaw Foundation.

 

 